TEN DAYS TO TRUSSES
Day 10:
Complete and Accurate Information to TCT
Day 9-7:
Design by TCT
(Length of design time depends on plan’s complexity.)
Day 6:
Complete layout, truss list, and truss drawings
(Provided for your review.)
Day 5:
Design finalized to "as-built" by TCT
Day 4:
Order Processing and Engineering Seals
Day 3:
Lumber sorted and cut
(Changes after this time may require restocking fee or new lumber purchase.)
Day 2:
Trusses built
(Changes after this time may require purchase of new trusses.)
Day 1:
Trusses arrive at site
(Overheight trusses traveling over the passes may be delayed by "overwidth" highway closures during the winter. Faster delivery needs may incur a 20% rush charge.)
There is no other fine print.